# Managed Network Services Takeover Timeline
|
# Hardware-Focused Network Services Takeover Timeline
|
||||||
|
|
||||||
Below is the project timeline for the transition from MSP A to MSP B, including a complete network upgrade.
|
Below is the project timeline for the transition from MSP A to MSP B, focusing on the hardware procurement and installation, with involvement from the distributor.
|
||||||
|
|
||||||
```mermaid
|
```mermaid
|
||||||
gantt
|
gantt
|
||||||
title Managed Network Services Takeover Timeline
|
title Hardware-Focused Network Services Takeover Timeline
|
||||||
dateFormat YYYY-MM-DD
|
dateFormat YYYY-MM-DD
|
||||||
axisFormat %m-%d
|
axisFormat %m-%d
|
||||||
excludes weekends
|
excludes weekends
|
||||||
|
|
||||||
section Planning and Preparation
|
section Planning and Preparation
|
||||||
Define Project Scope :a1, 2024-08-01, 7d
|
Define Hardware Requirements :a1, 2024-08-01, 7d
|
||||||
Requirements Gathering :a2, after a1, 10d
|
Stakeholder Approval :a2, after a1, 3d
|
||||||
Infrastructure Assessment :a3, after a2, 10d
|
|
||||||
Create Detailed Project Plan :a4, after a3, 7d
|
|
||||||
Stakeholder Approval :a5, after a4, 3d
|
|
||||||
|
|
||||||
section Procurement and Setup
|
section Procurement and Coordination
|
||||||
Order New Hardware :b1, 2024-09-01, 14d
|
Place Hardware Orders :b1, 2024-08-10, 5d
|
||||||
Receive and Inventory Equipment :b2, after b1, 7d
|
Distributor Processing :b2, after b1, 5d
|
||||||
License Procurement :b3, after b2, 5d
|
Orchestrate Shipments :b3, after b2, 7d
|
||||||
|
Delivery to Sites :b4, after b3, 14d
|
||||||
|
|
||||||
section Site Preparation
|
section Site Preparation
|
||||||
Site Surveys :c1, 2024-09-22, 10d
|
Site Surveys :c1, 2024-08-30, 10d
|
||||||
Pre-Installation Checks :c2, after c1, 5d
|
Pre-Installation Checks :c2, after c1, 5d
|
||||||
|
|
||||||
section Network Deployment
|
section Network Deployment
|
||||||
Decommission Old Equipment :d1, 2024-10-10, 5d
|
Decommission Old Equipment :d1, 2024-09-15, 5d
|
||||||
Install New Hardware :d2, after d1, 14d
|
Install New Hardware :d2, after d1, 14d
|
||||||
Initial Configuration and Testing :d3, after d2, 10d
|
Initial Configuration and Testing :d3, after d2, 10d
|
||||||
|
|
||||||
section Network Cutover
|
|
||||||
Pilot Branch Migration :e1, 2024-10-30, 5d
|
|
||||||
Validate Pilot Branch :e2, after e1, 3d
|
|
||||||
Full Branch Migration :e3, after e2, 20d
|
|
||||||
Post-Migration Validation :e4, after e3, 10d
|
|
||||||
|
|
||||||
section Finalization and Handover
|
section Finalization and Handover
|
||||||
Training and Documentation :f1, 2024-11-30, 7d
|
Training and Documentation :e1, 2024-10-10, 7d
|
||||||
Handover to Operations Team :f2, after f1, 5d
|
Handover to Operations Team :e2, after e1, 5d
|
||||||
Project Close-Out :f3, after f2, 3d
|
Project Close-Out :e3, after e2, 3d
|
||||||
```
|
```
|
||||||
|
|
||||||
|
|
||||||
|
|
||||||
### Detailed Breakdown
|
### Detailed Breakdown
|
||||||
|
|
||||||
#### Planning and Preparation (2024-08-01 to 2024-09-08)
|
#### Planning and Preparation (2024-08-01 to 2024-08-10)
|
||||||
1. **Define Project Scope**: Establish project objectives and deliverables.
|
1. **Define Hardware Requirements (2024-08-01 to 2024-08-07)**: Establish the specific hardware needs for the network upgrade, including routers, switches, access points, and security appliances.
|
||||||
2. **Requirements Gathering**: Identify technical and business needs.
|
2. **Stakeholder Approval (2024-08-08 to 2024-08-10)**: Obtain necessary approvals from stakeholders to proceed with hardware procurement.
|
||||||
3. **Infrastructure Assessment**: Evaluate current network setup.
|
|
||||||
4. **Create Project Plan**: Develop a comprehensive project plan.
|
|
||||||
5. **Stakeholder Approval**: Obtain necessary approvals.
|
|
||||||
|
|
||||||
#### Procurement and Setup (2024-09-01 to 2024-09-26)
|
#### Procurement and Coordination (2024-08-10 to 2024-09-04)
|
||||||
1. **Order New Hardware**: Procure all required networking equipment.
|
1. **Place Hardware Orders (2024-08-10 to 2024-08-15)**: Submit orders for all required hardware to the distributor.
|
||||||
2. **Receive and Inventory Equipment**: Inspect and catalog equipment.
|
2. **Distributor Processing (2024-08-16 to 2024-08-21)**: The distributor processes orders, confirming availability and preparing for shipment.
|
||||||
3. **License Procurement**: Acquire necessary licenses for new hardware.
|
3. **Orchestrate Shipments (2024-08-22 to 2024-08-29)**: The distributor coordinates shipments to various sites, ensuring timely delivery.
|
||||||
|
4. **Delivery to Sites (2024-08-30 to 2024-09-12)**: Hardware is delivered to all installation sites.
|
||||||
|
|
||||||
#### Site Preparation (2024-09-22 to 2024-10-07)
|
#### Site Preparation (2024-08-30 to 2024-09-14)
|
||||||
1. **Site Surveys**: Conduct surveys to determine hardware placement.
|
1. **Site Surveys (2024-08-30 to 2024-09-09)**: Conduct surveys at each site to determine optimal hardware placement.
|
||||||
2. **Pre-Installation Checks**: Ensure sites are ready for installation.
|
2. **Pre-Installation Checks (2024-09-10 to 2024-09-14)**: Perform checks to ensure sites are ready for hardware installation.
|
||||||
|
|
||||||
#### Network Deployment (2024-10-10 to 2024-11-07)
|
#### Network Deployment (2024-09-15 to 2024-10-09)
|
||||||
1. **Decommission Old Equipment**: Remove outdated network devices.
|
1. **Decommission Old Equipment (2024-09-15 to 2024-09-19)**: Remove outdated network devices from all sites.
|
||||||
2. **Install New Hardware**: Set up new networking equipment.
|
2. **Install New Hardware (2024-09-20 to 2024-10-03)**: Set up new networking equipment at all sites.
|
||||||
3. **Initial Configuration and Testing**: Configure and test the new network.
|
3. **Initial Configuration and Testing (2024-10-04 to 2024-10-09)**: Configure and test the new network hardware to ensure proper operation.
|
||||||
|
|
||||||
#### Network Cutover (2024-10-30 to 2024-12-08)
|
#### Finalization and Handover (2024-10-10 to 2024-10-25)
|
||||||
1. **Pilot Branch Migration**: Transition a pilot branch to the new network.
|
1. **Training and Documentation (2024-10-10 to 2024-10-16)**: Provide necessary training and documentation to the operations team.
|
||||||
2. **Validate Pilot Branch**: Ensure pilot branch operates correctly.
|
2. **Handover to Operations Team (2024-10-17 to 2024-10-21)**: Officially transfer management of the new network hardware to the operations team.
|
||||||
3. **Full Branch Migration**: Transition all branches to the new network.
|
3. **Project Close-Out (2024-10-22 to 2024-10-25)**: Complete all project close-out activities, including final documentation and lessons learned.
|
||||||
4. **Post-Migration Validation**: Verify network functionality post-migration.
|
|
||||||
|
|
||||||
#### Finalization and Handover (2024-11-30 to 2024-12-14)
|
This timeline focuses on the essential hardware aspects of the network services takeover, ensuring smooth procurement, delivery, and installation coordinated by the distributor.
|
||||||
1. **Training and Documentation**: Provide necessary training and documentation.
|
|
||||||
2. **Handover to Operations Team**: Officially transfer network management.
|
|
||||||
3. **Project Close-Out**: Finalize all project activities and documentation.
|
|
||||||
|
|
||||||
This timeline provides a clear and concise overview of the major phases and tasks involved in the managed network services takeover, ensuring readability and ease of understanding.
|
|
||||||
|
|||||||