# Managed Network Services Takeover Timeline Below is the project timeline for the transition from MSP A to MSP B, including a complete network upgrade. ```mermaid gantt title Managed Network Services Takeover Timeline dateFormat YYYY-MM-DD axisFormat %m-%d excludes weekends section Planning and Preparation Define Project Scope :a1, 2024-08-01, 7d Requirements Gathering :a2, after a1, 10d Infrastructure Assessment :a3, after a2, 10d Create Detailed Project Plan :a4, after a3, 7d Stakeholder Approval :a5, after a4, 3d section Procurement and Setup Order New Hardware :b1, 2024-09-01, 14d Receive and Inventory Equipment :b2, after b1, 7d License Procurement :b3, after b2, 5d section Site Preparation Site Surveys :c1, 2024-09-22, 10d Pre-Installation Checks :c2, after c1, 5d section Network Deployment Decommission Old Equipment :d1, 2024-10-10, 5d Install New Hardware :d2, after d1, 14d Initial Configuration and Testing :d3, after d2, 10d section Network Cutover Pilot Branch Migration :e1, 2024-10-30, 5d Validate Pilot Branch :e2, after e1, 3d Full Branch Migration :e3, after e2, 20d Post-Migration Validation :e4, after e3, 10d section Finalization and Handover Training and Documentation :f1, 2024-11-30, 7d Handover to Operations Team :f2, after f1, 5d Project Close-Out :f3, after f2, 3d ``` --- ### Detailed Breakdown #### Planning and Preparation - **Define Project Scope (2024-08-01 to 2024-08-07)**: Establish the project’s objectives, deliverables, and constraints. - **Requirements Gathering (2024-08-08 to 2024-08-18)**: Identify all technical and business requirements for the new network. - **Infrastructure Assessment (2024-08-19 to 2024-08-29)**: Assess the current network infrastructure to plan the rip and replace strategy. - **Create Detailed Project Plan (2024-08-30 to 2024-09-05)**: Develop a comprehensive project plan, including timelines, resources, and risk management. - **Stakeholder Approval (2024-09-06 to 2024-09-08)**: Obtain approval from all stakeholders to proceed with the project. #### Procurement and Setup - **Order New Hardware (2024-09-01 to 2024-09-14)**: Place orders for all new networking equipment. - **Receive and Inventory Equipment (2024-09-15 to 2024-09-21)**: Receive, inspect, and inventory all equipment. - **License Procurement (2024-09-22 to 2024-09-26)**: Procure necessary licenses for the new hardware and software. #### Site Preparation - **Site Surveys (2024-09-22 to 2024-10-02)**: Conduct site surveys to determine optimal hardware placement. - **Pre-Installation Checks (2024-10-03 to 2024-10-07)**: Perform checks to ensure sites are ready for installation. #### Network Deployment - **Decommission Old Equipment (2024-10-10 to 2024-10-14)**: Remove old network equipment. - **Install New Hardware (2024-10-15 to 2024-10-28)**: Install the new networking hardware. - **Initial Configuration and Testing (2024-10-29 to 2024-11-07)**: Configure and test the new network setup. #### Network Cutover - **Pilot Branch Migration (2024-10-30 to 2024-11-03)**: Migrate a pilot branch to the new network to validate the process. - **Validate Pilot Branch (2024-11-04 to 2024-11-06)**: Ensure the pilot branch is operating correctly. - **Full Branch Migration (2024-11-07 to 2024-11-27)**: Migrate all remaining branches to the new network. - **Post-Migration Validation (2024-11-28 to 2024-12-08)**: Validate the operation of all branches post-migration. #### Finalization and Handover - **Training and Documentation (2024-11-30 to 2024-12-06)**: Provide training and documentation to the operations team. - **Handover to Operations Team (2024-12-07 to 2024-12-11)**: Officially hand over