# Managed Network Services Takeover Timeline Below is the project timeline for the transition from MSP A to MSP B, including a complete network upgrade. ```mermaid gantt title Managed Network Services Takeover Timeline dateFormat YYYY-MM-DD axisFormat %m-%d excludes weekends section Planning and Preparation Define Project Scope :a1, 2024-08-01, 7d Requirements Gathering :a2, after a1, 10d Infrastructure Assessment :a3, after a2, 10d Create Detailed Project Plan :a4, after a3, 7d Stakeholder Approval :a5, after a4, 3d section Procurement and Setup Order New Hardware :b1, 2024-09-01, 14d Receive and Inventory Equipment :b2, after b1, 7d License Procurement :b3, after b2, 5d section Site Preparation Site Surveys :c1, 2024-09-22, 10d Pre-Installation Checks :c2, after c1, 5d section Network Deployment Decommission Old Equipment :d1, 2024-10-10, 5d Install New Hardware :d2, after d1, 14d Initial Configuration and Testing :d3, after d2, 10d section Network Cutover Pilot Branch Migration :e1, 2024-10-30, 5d Validate Pilot Branch :e2, after e1, 3d Full Branch Migration :e3, after e2, 20d Post-Migration Validation :e4, after e3, 10d section Finalization and Handover Training and Documentation :f1, 2024-11-30, 7d Handover to Operations Team :f2, after f1, 5d Project Close-Out :f3, after f2, 3d ``` ### Detailed Breakdown #### Planning and Preparation (2024-08-01 to 2024-09-08) 1. **Define Project Scope**: Establish project objectives and deliverables. 2. **Requirements Gathering**: Identify technical and business needs. 3. **Infrastructure Assessment**: Evaluate current network setup. 4. **Create Project Plan**: Develop a comprehensive project plan. 5. **Stakeholder Approval**: Obtain necessary approvals. #### Procurement and Setup (2024-09-01 to 2024-09-26) 1. **Order New Hardware**: Procure all required networking equipment. 2. **Receive and Inventory Equipment**: Inspect and catalog equipment. 3. **License Procurement**: Acquire necessary licenses for new hardware. #### Site Preparation (2024-09-22 to 2024-10-07) 1. **Site Surveys**: Conduct surveys to determine hardware placement. 2. **Pre-Installation Checks**: Ensure sites are ready for installation. #### Network Deployment (2024-10-10 to 2024-11-07) 1. **Decommission Old Equipment**: Remove outdated network devices. 2. **Install New Hardware**: Set up new networking equipment. 3. **Initial Configuration and Testing**: Configure and test the new network. #### Network Cutover (2024-10-30 to 2024-12-08) 1. **Pilot Branch Migration**: Transition a pilot branch to the new network. 2. **Validate Pilot Branch**: Ensure pilot branch operates correctly. 3. **Full Branch Migration**: Transition all branches to the new network. 4. **Post-Migration Validation**: Verify network functionality post-migration. #### Finalization and Handover (2024-11-30 to 2024-12-14) 1. **Training and Documentation**: Provide necessary training and documentation. 2. **Handover to Operations Team**: Officially transfer network management. 3. **Project Close-Out**: Finalize all project activities and documentation. This timeline provides a clear and concise overview of the major phases and tasks involved in the managed network services takeover, ensuring readability and ease of understanding.