Here's a detailed timeline for the managed takeover where MSP B takes over from MSP A, involving a complete rip and replace of the network with an OEM to OEM direct upgrade. This timeline is presented in Mermaid syntax for easy visualization in Markdown.
|
||||
|
||||
### Project Timeline for Managed Network Services Takeover
|
||||
|
||||
```markdown
|
||||
# Managed Network Services Takeover Timeline
|
||||
|
||||
Below is the project timeline for the transition from MSP A to MSP B, including a complete network upgrade.
|
||||
|
||||
```mermaid
|
||||
gantt
|
||||
title Managed Network Services Takeover Timeline
|
||||
dateFormat YYYY-MM-DD
|
||||
axisFormat %m-%d
|
||||
excludes weekends
|
||||
|
||||
section Planning and Preparation
|
||||
Define Project Scope :a1, 2024-08-01, 7d
|
||||
Requirements Gathering :a2, after a1, 10d
|
||||
Infrastructure Assessment :a3, after a2, 10d
|
||||
Create Detailed Project Plan :a4, after a3, 7d
|
||||
Stakeholder Approval :a5, after a4, 3d
|
||||
|
||||
section Procurement and Setup
|
||||
Order New Hardware :b1, 2024-09-01, 14d
|
||||
Receive and Inventory Equipment :b2, after b1, 7d
|
||||
License Procurement :b3, parallel with b2, 5d
|
||||
|
||||
section Site Preparation
|
||||
Site Surveys :c1, 2024-09-22, 10d
|
||||
Pre-Installation Checks :c2, after c1, 5d
|
||||
|
||||
section Network Deployment
|
||||
Decommission Old Equipment :d1, 2024-10-10, 5d
|
||||
Install New Hardware :d2, after d1, 14d
|
||||
Initial Configuration and Testing :d3, parallel with d2, 10d
|
||||
|
||||
section Network Cutover
|
||||
Pilot Branch Migration :e1, 2024-10-30, 5d
|
||||
Validate Pilot Branch :e2, after e1, 3d
|
||||
Full Branch Migration :e3, after e2, 20d
|
||||
Post-Migration Validation :e4, parallel with e3, 10d
|
||||
|
||||
section Finalization and Handover
|
||||
Training and Documentation :f1, 2024-11-30, 7d
|
||||
Handover to Operations Team :f2, after f1, 5d
|
||||
Project Close-Out :f3, after f2, 3d
|
||||
```
|
||||
```
|
||||
|
||||
### Detailed Breakdown
|
||||
|
||||
#### Planning and Preparation
|
||||
- **Define Project Scope (2024-08-01 to 2024-08-07)**: Establish the project’s objectives, deliverables, and constraints.
|
||||
- **Requirements Gathering (2024-08-08 to 2024-08-18)**: Identify all technical and business requirements for the new network.
|
||||
- **Infrastructure Assessment (2024-08-19 to 2024-08-29)**: Assess the current network infrastructure to plan the rip and replace strategy.
|
||||
- **Create Detailed Project Plan (2024-08-30 to 2024-09-05)**: Develop a comprehensive project plan, including timelines, resources, and risk management.
|
||||
- **Stakeholder Approval (2024-09-06 to 2024-09-08)**: Obtain approval from all stakeholders to proceed with the project.
|
||||
|
||||
#### Procurement and Setup
|
||||
- **Order New Hardware (2024-09-01 to 2024-09-14)**: Place orders for all new networking equipment.
|
||||
- **Receive and Inventory Equipment (2024-09-15 to 2024-09-21)**: Receive, inspect, and inventory all equipment.
|
||||
- **License Procurement (2024-09-15 to 2024-09-19)**: Procure necessary licenses for the new hardware and software.
|
||||
|
||||
#### Site Preparation
|
||||
- **Site Surveys (2024-09-22 to 2024-10-02)**: Conduct site surveys to determine optimal hardware placement.
|
||||
- **Pre-Installation Checks (2024-10-03 to 2024-10-07)**: Perform checks to ensure sites are ready for installation.
|
||||
|
||||
#### Network Deployment
|
||||
- **Decommission Old Equipment (2024-10-10 to 2024-10-14)**: Remove old network equipment.
|
||||
- **Install New Hardware (2024-10-15 to 2024-10-28)**: Install the new networking hardware.
|
||||
- **Initial Configuration and Testing (2024-10-15 to 2024-10-24)**: Configure and test the new network setup.
|
||||
|
||||
#### Network Cutover
|
||||
- **Pilot Branch Migration (2024-10-30 to 2024-11-03)**: Migrate a pilot branch to the new network to validate the process.
|
||||
- **Validate Pilot Branch (2024-11-04 to 2024-11-06)**: Ensure the pilot branch is operating correctly.
|
||||
- **Full Branch Migration (2024-11-07 to 2024-11-27)**: Migrate all remaining branches to the new network.
|
||||
- **Post-Migration Validation (2024-11-07 to 2024-11-17)**: Validate the operation of all branches post-migration.
|
||||
|
||||
#### Finalization and Handover
|
||||
- **Training and Documentation (2024-11-30 to 2024-12-06)**: Provide training and documentation to the operations team.
|
||||
- **Handover to Operations Team (2024-12-07 to 2024-12-11)**: Officially hand over the new network to the operations team.
|
||||
- **Project Close-Out (2024-12-12 to 2024-12-14)**: Complete project close-out activities, including final documentation and lessons learned.
|
||||
|
||||
This timeline outlines a structured approach to transitioning network management from one service provider to another, ensuring all critical phases are addressed for a smooth and efficient process.
|
||||