Creating a timeline using Mermaid in Markdown is a great way to visually represent a project timeline. Mermaid provides a simple syntax for creating timelines, and you can embed these diagrams directly in Markdown. Here’s a guide to help you get started:
|
||||
|
||||
### Mermaid Timeline Syntax
|
||||
|
||||
To create a timeline in Mermaid, you can use the `gantt` chart. Here are the basic components and options:
|
||||
|
||||
1. **Basic Structure**:
|
||||
```markdown
|
||||
```mermaid
|
||||
gantt
|
||||
title Your Project Timeline
|
||||
dateFormat YYYY-MM-DD
|
||||
section Section 1
|
||||
Task 1 :a1, 2024-07-01, 30d
|
||||
Task 2 :after a1 , 20d
|
||||
section Section 2
|
||||
Task 3 :2024-08-01 , 12d
|
||||
Task 4 :2024-08-15 , 18d
|
||||
```
|
||||
```
|
||||
|
||||
2. **Components**:
|
||||
- `title`: Sets the title of your Gantt chart.
|
||||
- `dateFormat`: Specifies the date format. Common formats include `YYYY-MM-DD`.
|
||||
- `section`: Defines a new section in the timeline.
|
||||
- `Task`: Defines a task within a section. The syntax is `Task Name :task_id, start_date, duration`.
|
||||
- `task_id`: An optional identifier for the task, used for dependencies.
|
||||
- `start_date`: The start date of the task. Use `after task_id` to start after another task.
|
||||
- `duration`: The duration of the task (e.g., `30d` for 30 days).
|
||||
|
||||
### Example Timeline
|
||||
|
||||
Here's a detailed example to illustrate how to create a project timeline:
|
||||
|
||||
```markdown
|
||||
```mermaid
|
||||
gantt
|
||||
title Project Timeline Example
|
||||
dateFormat YYYY-MM-DD
|
||||
axisFormat %m-%d
|
||||
excludes weekends
|
||||
|
||||
section Planning
|
||||
Define Scope :a1, 2024-07-01, 10d
|
||||
Requirements :a2, after a1, 7d
|
||||
|
||||
section Development
|
||||
Setup Environment :a3, 2024-07-15, 5d
|
||||
Develop Features :a4, after a3, 20d
|
||||
Testing :a5, after a4, 10d
|
||||
|
||||
section Deployment
|
||||
Deploy to Staging :a6, 2024-08-20, 3d
|
||||
UAT :a7, after a6, 7d
|
||||
Final Deployment :a8, after a7, 2d
|
||||
```
|
||||
```
|
||||
|
||||
### Options and Customization
|
||||
|
||||
- **axisFormat**: Changes the format of the dates displayed on the axis. For example, `%m-%d` shows month-day format.
|
||||
- **excludes**: Specifies days to exclude from the timeline, like `weekends`.
|
||||
- **taskColor**: You can specify custom colors for tasks. Example syntax:
|
||||
```mermaid
|
||||
gantt
|
||||
title Customized Timeline
|
||||
dateFormat YYYY-MM-DD
|
||||
section Development
|
||||
Setup Environment :a1, 2024-07-01, 5d, color: blue
|
||||
Develop Features :a2, after a1, 20d, color: red
|
||||
```
|
||||
|
||||
### Implementing in Markdown
|
||||
|
||||
To embed the timeline in Markdown, use triple backticks followed by `mermaid`, then add your Gantt chart syntax, and close with triple backticks. Here's an example:
|
||||
|
||||
```markdown
|
||||
# Project Timeline
|
||||
|
||||
Below is the project timeline for our upcoming tasks:
|
||||
|
||||
```mermaid
|
||||
gantt
|
||||
title Project Timeline
|
||||
dateFormat YYYY-MM-DD
|
||||
|
||||
section Phase 1
|
||||
Task 1 :a1, 2024-07-01, 10d
|
||||
Task 2 :after a1, 5d
|
||||
|
||||
section Phase 2
|
||||
Task 3 :2024-07-15, 7d
|
||||
Task 4 :after a3, 3d
|
||||
```
|
||||
```
|
||||
|
||||
This will render the Gantt chart when viewed in a Markdown renderer that supports Mermaid diagrams, such as GitHub or VSCode with the appropriate extensions.
|
||||
|
||||
Feel free to modify the sections, tasks, dates, and durations to fit your project's timeline.
|
||||