Creating a timeline using Mermaid in Markdown is a great way to visually represent a project timeline. Mermaid provides a simple syntax for creating timelines, and you can embed these diagrams directly in Markdown. Here’s a guide to help you get started:
Mermaid Timeline Syntax
To create a timeline in Mermaid, you can use the gantt chart. Here are the basic components and options:
-
Basic Structure:
gantt title Your Project Timeline dateFormat YYYY-MM-DD section Section 1 Task 1 :a1, 2024-07-01, 30d Task 2 :after a1 , 20d section Section 2 Task 3 :2024-08-01 , 12d Task 4 :2024-08-15 , 18d -
Components:
title: Sets the title of your Gantt chart.dateFormat: Specifies the date format. Common formats includeYYYY-MM-DD.section: Defines a new section in the timeline.Task: Defines a task within a section. The syntax isTask Name :task_id, start_date, duration.task_id: An optional identifier for the task, used for dependencies.start_date: The start date of the task. Useafter task_idto start after another task.duration: The duration of the task (e.g.,30dfor 30 days).
Example Timeline
Here's a detailed example to illustrate how to create a project timeline:
gantt
title Project Timeline Example
dateFormat YYYY-MM-DD
axisFormat %m-%d
excludes weekends
section Planning
Define Scope :a1, 2024-07-01, 10d
Requirements :a2, after a1, 7d
section Development
Setup Environment :a3, 2024-07-15, 5d
Develop Features :a4, after a3, 20d
Testing :a5, after a4, 10d
section Deployment
Deploy to Staging :a6, 2024-08-20, 3d
UAT :a7, after a6, 7d
Final Deployment :a8, after a7, 2d
Options and Customization
-
axisFormat: Changes the format of the dates displayed on the axis. For example,
%m-%dshows month-day format. -
excludes: Specifies days to exclude from the timeline, like
weekends. -
taskColor: You can specify custom colors for tasks. Example syntax:
gantt title Customized Timeline dateFormat YYYY-MM-DD section Development Setup Environment :a1, 2024-07-01, 5d, color: blue Develop Features :a2, after a1, 20d, color: red
Implementing in Markdown
To embed the timeline in Markdown, use triple backticks followed by mermaid, then add your Gantt chart syntax, and close with triple backticks. Here's an example:
Project Timeline
Below is the project timeline for our upcoming tasks:
gantt
title Project Timeline
dateFormat YYYY-MM-DD
section Phase 1
Task 1 :a1, 2024-07-01, 10d
Task 2 :after a1, 5d
section Phase 2
Task 3 :2024-07-15, 7d
Task 4 :after a3, 3d
This will render the Gantt chart when viewed in a Markdown renderer that supports Mermaid diagrams, such as GitHub or VSCode with the appropriate extensions.
Feel free to modify the sections, tasks, dates, and durations to fit your project's timeline.