# Hardware-Focused Network Services Takeover Timeline
|
|
|
|
Below is the project timeline for the transition from MSP A to MSP B, focusing on the hardware procurement and installation, with involvement from the distributor.
|
|
|
|
```mermaid
|
|
gantt
|
|
title Hardware-Focused Network Services Takeover Timeline
|
|
dateFormat YYYY-MM-DD
|
|
axisFormat %m-%d
|
|
excludes weekends
|
|
|
|
section Planning and Preparation
|
|
Define Hardware Requirements :a1, 2024-08-01, 7d
|
|
Stakeholder Approval :a2, after a1, 3d
|
|
|
|
section Procurement and Coordination
|
|
Place Hardware Orders :b1, 2024-08-10, 5d
|
|
Distributor Processing :b2, after b1, 5d
|
|
Orchestrate Shipments :b3, after b2, 7d
|
|
Delivery to Sites :b4, after b3, 14d
|
|
|
|
section Site Preparation
|
|
Site Surveys :c1, 2024-08-30, 10d
|
|
Pre-Installation Checks :c2, after c1, 5d
|
|
|
|
section Network Deployment
|
|
Decommission Old Equipment :d1, 2024-09-15, 5d
|
|
Install New Hardware :d2, after d1, 14d
|
|
Initial Configuration and Testing :d3, after d2, 10d
|
|
|
|
section Finalization and Handover
|
|
Training and Documentation :e1, 2024-10-10, 7d
|
|
Handover to Operations Team :e2, after e1, 5d
|
|
Project Close-Out :e3, after e2, 3d
|
|
```
|
|
|
|
|
|
|
|
### Detailed Breakdown
|
|
|
|
#### Planning and Preparation (2024-08-01 to 2024-08-10)
|
|
1. **Define Hardware Requirements (2024-08-01 to 2024-08-07)**: Establish the specific hardware needs for the network upgrade, including routers, switches, access points, and security appliances.
|
|
2. **Stakeholder Approval (2024-08-08 to 2024-08-10)**: Obtain necessary approvals from stakeholders to proceed with hardware procurement.
|
|
|
|
#### Procurement and Coordination (2024-08-10 to 2024-09-04)
|
|
1. **Place Hardware Orders (2024-08-10 to 2024-08-15)**: Submit orders for all required hardware to the distributor.
|
|
2. **Distributor Processing (2024-08-16 to 2024-08-21)**: The distributor processes orders, confirming availability and preparing for shipment.
|
|
3. **Orchestrate Shipments (2024-08-22 to 2024-08-29)**: The distributor coordinates shipments to various sites, ensuring timely delivery.
|
|
4. **Delivery to Sites (2024-08-30 to 2024-09-12)**: Hardware is delivered to all installation sites.
|
|
|
|
#### Site Preparation (2024-08-30 to 2024-09-14)
|
|
1. **Site Surveys (2024-08-30 to 2024-09-09)**: Conduct surveys at each site to determine optimal hardware placement.
|
|
2. **Pre-Installation Checks (2024-09-10 to 2024-09-14)**: Perform checks to ensure sites are ready for hardware installation.
|
|
|
|
#### Network Deployment (2024-09-15 to 2024-10-09)
|
|
1. **Decommission Old Equipment (2024-09-15 to 2024-09-19)**: Remove outdated network devices from all sites.
|
|
2. **Install New Hardware (2024-09-20 to 2024-10-03)**: Set up new networking equipment at all sites.
|
|
3. **Initial Configuration and Testing (2024-10-04 to 2024-10-09)**: Configure and test the new network hardware to ensure proper operation.
|
|
|
|
#### Finalization and Handover (2024-10-10 to 2024-10-25)
|
|
1. **Training and Documentation (2024-10-10 to 2024-10-16)**: Provide necessary training and documentation to the operations team.
|
|
2. **Handover to Operations Team (2024-10-17 to 2024-10-21)**: Officially transfer management of the new network hardware to the operations team.
|
|
3. **Project Close-Out (2024-10-22 to 2024-10-25)**: Complete all project close-out activities, including final documentation and lessons learned.
|
|
|
|
This timeline focuses on the essential hardware aspects of the network services takeover, ensuring smooth procurement, delivery, and installation coordinated by the distributor.
|