@@ -2,7 +2,6 @@ Here's a detailed timeline for the managed takeover where MSP B takes over from
### Project Timeline for Managed Network Services Takeover
```markdown
# Managed Network Services Takeover Timeline
Below is the project timeline for the transition from MSP A to MSP B, including a complete network upgrade.
@@ -46,7 +45,6 @@ gantt
Handover to Operations Team :f2, after f1, 5d
Project Close-Out :f3, after f2, 3d
```
```
### Detailed Breakdown