Update work/tbx/swanson.md

This commit is contained in:
2024-07-18 15:54:01 +00:00
parent 793c09aa67
commit 2f666a6cfe

View File

@@ -2,7 +2,6 @@ Here's a detailed timeline for the managed takeover where MSP B takes over from
### Project Timeline for Managed Network Services Takeover ### Project Timeline for Managed Network Services Takeover
```markdown
# Managed Network Services Takeover Timeline # Managed Network Services Takeover Timeline
Below is the project timeline for the transition from MSP A to MSP B, including a complete network upgrade. Below is the project timeline for the transition from MSP A to MSP B, including a complete network upgrade.
@@ -46,7 +45,6 @@ gantt
Handover to Operations Team :f2, after f1, 5d Handover to Operations Team :f2, after f1, 5d
Project Close-Out :f3, after f2, 3d Project Close-Out :f3, after f2, 3d
``` ```
```
### Detailed Breakdown ### Detailed Breakdown