Managed Network Services Takeover Timeline
Below is the project timeline for the transition from MSP A to MSP B, including a complete network upgrade.
gantt
title Managed Network Services Takeover Timeline
dateFormat YYYY-MM-DD
axisFormat %m-%d
excludes weekends
section Planning and Preparation
Define Project Scope :a1, 2024-08-01, 7d
Requirements Gathering :a2, after a1, 10d
Infrastructure Assessment :a3, after a2, 10d
Create Detailed Project Plan :a4, after a3, 7d
Stakeholder Approval :a5, after a4, 3d
section Procurement and Setup
Order New Hardware :b1, 2024-09-01, 14d
Receive and Inventory Equipment :b2, after b1, 7d
License Procurement :b3, after b2, 5d
section Site Preparation
Site Surveys :c1, 2024-09-22, 10d
Pre-Installation Checks :c2, after c1, 5d
section Network Deployment
Decommission Old Equipment :d1, 2024-10-10, 5d
Install New Hardware :d2, after d1, 14d
Initial Configuration and Testing :d3, after d2, 10d
section Network Cutover
Pilot Branch Migration :e1, 2024-10-30, 5d
Validate Pilot Branch :e2, after e1, 3d
Full Branch Migration :e3, after e2, 20d
Post-Migration Validation :e4, after e3, 10d
section Finalization and Handover
Training and Documentation :f1, 2024-11-30, 7d
Handover to Operations Team :f2, after f1, 5d
Project Close-Out :f3, after f2, 3d
Detailed Breakdown
Planning and Preparation (2024-08-01 to 2024-09-08)
- Define Project Scope: Establish project objectives and deliverables.
- Requirements Gathering: Identify technical and business needs.
- Infrastructure Assessment: Evaluate current network setup.
- Create Project Plan: Develop a comprehensive project plan.
- Stakeholder Approval: Obtain necessary approvals.
Procurement and Setup (2024-09-01 to 2024-09-26)
- Order New Hardware: Procure all required networking equipment.
- Receive and Inventory Equipment: Inspect and catalog equipment.
- License Procurement: Acquire necessary licenses for new hardware.
Site Preparation (2024-09-22 to 2024-10-07)
- Site Surveys: Conduct surveys to determine hardware placement.
- Pre-Installation Checks: Ensure sites are ready for installation.
Network Deployment (2024-10-10 to 2024-11-07)
- Decommission Old Equipment: Remove outdated network devices.
- Install New Hardware: Set up new networking equipment.
- Initial Configuration and Testing: Configure and test the new network.
Network Cutover (2024-10-30 to 2024-12-08)
- Pilot Branch Migration: Transition a pilot branch to the new network.
- Validate Pilot Branch: Ensure pilot branch operates correctly.
- Full Branch Migration: Transition all branches to the new network.
- Post-Migration Validation: Verify network functionality post-migration.
Finalization and Handover (2024-11-30 to 2024-12-14)
- Training and Documentation: Provide necessary training and documentation.
- Handover to Operations Team: Officially transfer network management.
- Project Close-Out: Finalize all project activities and documentation.
This timeline provides a clear and concise overview of the major phases and tasks involved in the managed network services takeover, ensuring readability and ease of understanding.