# Managed Network Services Takeover Timeline
|
||
|
||
Below is the project timeline for the transition from MSP A to MSP B, including a complete network upgrade.
|
||
|
||
```mermaid
|
||
gantt
|
||
title Managed Network Services Takeover Timeline
|
||
dateFormat YYYY-MM-DD
|
||
axisFormat %m-%d
|
||
excludes weekends
|
||
|
||
section Planning and Preparation
|
||
Define Project Scope :a1, 2024-08-01, 7d
|
||
Requirements Gathering :a2, after a1, 10d
|
||
Infrastructure Assessment :a3, after a2, 10d
|
||
Create Detailed Project Plan :a4, after a3, 7d
|
||
Stakeholder Approval :a5, after a4, 3d
|
||
|
||
section Procurement and Setup
|
||
Order New Hardware :b1, 2024-09-01, 14d
|
||
Receive and Inventory Equipment :b2, after b1, 7d
|
||
License Procurement :b3, after b2, 5d
|
||
|
||
section Site Preparation
|
||
Site Surveys :c1, 2024-09-22, 10d
|
||
Pre-Installation Checks :c2, after c1, 5d
|
||
|
||
section Network Deployment
|
||
Decommission Old Equipment :d1, 2024-10-10, 5d
|
||
Install New Hardware :d2, after d1, 14d
|
||
Initial Configuration and Testing :d3, after d2, 10d
|
||
|
||
section Network Cutover
|
||
Pilot Branch Migration :e1, 2024-10-30, 5d
|
||
Validate Pilot Branch :e2, after e1, 3d
|
||
Full Branch Migration :e3, after e2, 20d
|
||
Post-Migration Validation :e4, after e3, 10d
|
||
|
||
section Finalization and Handover
|
||
Training and Documentation :f1, 2024-11-30, 7d
|
||
Handover to Operations Team :f2, after f1, 5d
|
||
Project Close-Out :f3, after f2, 3d
|
||
|
||
|
||
---
|
||
|
||
|
||
### Detailed Breakdown
|
||
|
||
#### Planning and Preparation
|
||
- **Define Project Scope (2024-08-01 to 2024-08-07)**: Establish the project’s objectives, deliverables, and constraints.
|
||
- **Requirements Gathering (2024-08-08 to 2024-08-18)**: Identify all technical and business requirements for the new network.
|
||
- **Infrastructure Assessment (2024-08-19 to 2024-08-29)**: Assess the current network infrastructure to plan the rip and replace strategy.
|
||
- **Create Detailed Project Plan (2024-08-30 to 2024-09-05)**: Develop a comprehensive project plan, including timelines, resources, and risk management.
|
||
- **Stakeholder Approval (2024-09-06 to 2024-09-08)**: Obtain approval from all stakeholders to proceed with the project.
|
||
|
||
#### Procurement and Setup
|
||
- **Order New Hardware (2024-09-01 to 2024-09-14)**: Place orders for all new networking equipment.
|
||
- **Receive and Inventory Equipment (2024-09-15 to 2024-09-21)**: Receive, inspect, and inventory all equipment.
|
||
- **License Procurement (2024-09-22 to 2024-09-26)**: Procure necessary licenses for the new hardware and software.
|
||
|
||
#### Site Preparation
|
||
- **Site Surveys (2024-09-22 to 2024-10-02)**: Conduct site surveys to determine optimal hardware placement.
|
||
- **Pre-Installation Checks (2024-10-03 to 2024-10-07)**: Perform checks to ensure sites are ready for installation.
|
||
|
||
#### Network Deployment
|
||
- **Decommission Old Equipment (2024-10-10 to 2024-10-14)**: Remove old network equipment.
|
||
- **Install New Hardware (2024-10-15 to 2024-10-28)**: Install the new networking hardware.
|
||
- **Initial Configuration and Testing (2024-10-29 to 2024-11-07)**: Configure and test the new network setup.
|
||
|
||
#### Network Cutover
|
||
- **Pilot Branch Migration (2024-10-30 to 2024-11-03)**: Migrate a pilot branch to the new network to validate the process.
|
||
- **Validate Pilot Branch (2024-11-04 to 2024-11-06)**: Ensure the pilot branch is operating correctly.
|
||
- **Full Branch Migration (2024-11-07 to 2024-11-27)**: Migrate all remaining branches to the new network.
|
||
- **Post-Migration Validation (2024-11-28 to 2024-12-08)**: Validate the operation of all branches post-migration.
|
||
|
||
#### Finalization and Handover
|
||
- **Training and Documentation (2024-11-30 to 2024-12-06)**: Provide training and documentation to the operations team.
|
||
- **Handover to Operations Team (2024-12-07 to 2024-12-11)**: Officially hand over
|